Over 3 km of Padma Bridge visible as 21st span installed

DHAKA, – The 21st span of the much-awaited Padma Multipurpose Bridge was installed today at Jajira point, making over 3 kilometres out of total 6.15km of the main structure of the bridge visible. “The 21st span among the total 41 was placed between the 32nd and the 33rd pillars at the Jajira point of the bridge around 3:00 pm,” said Dewan Abdul Quader, an executive engineer of the Padma Bridge Project. Earlier, the 20th span was installed on pillars 18-19 to complete 3km of the bridge on December 31, 2019. The … Continue reading Over 3 km of Padma Bridge visible as 21st span installed